Stephanie Barrett

Our specialty is in construction accounting, we contract with many businesses, offering a variety of accounting/payroll needs. In addition to accounting & bookkeeping services, we offer Public Relations work for job specific road/bridge construction and lease out fully operational office trailers.

The following in the anticipated schedule for the I-91 Rockingham Bridges

Written by on June 15, 2018 in Rockingham Bridges-I91

For the week beginning, June 18, 2018:

I-91 northbound bridge activities:

 Monday thru Friday – Daytime:

 I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

At approx.. 8:00am and 11:00am southbound for approximately 30 minutes

At approx.. 10:00am and 2:00pm northbound* for approximately 30 minutes

Please note rolling road block times could vary due to unforeseen circumstances.

* The northbound rolling road blocks also include the Exit 6 on ramp.  Motorists may want to follow the detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.  Oversize trucks must follow their permitted route. 

  • Continued beam erection
  • Complete removing forms from Abutment 1
  • Cleanup of Abutment 1 and begin backfilling
  • Truck traffic on Golden Hill Road

 

 

The following is the anticipated schedule for VT Route 2A & US 2 project:

Currently, there isn’t any work scheduled for this project until July 2, 2018.

The following is the anticipated work schedule for the VT 116 project:

Written by on June 14, 2018 in Middlebury-Starksboro VT 116

The anticipated work schedule for the week beginning Monday,  June 18, 2018:

 Monday thru Friday:

  • Continued ditch work. Between East Middlebury and Bristol
  • Sign installation from the “Lord’s Prayer Rock” to Starksboro

Traffic control will be present allowing for one lane of alternating traffic within the construction packages.

The following is the anticipated work schedule for Bridge #8 on VT 17

Written by on June 14, 2018 in BRIDGE 8 VT ROUTE 17
The following is the anticipated work schedule for Bridge #8 on VT 17

BRIDGE #8 ON VT ROUTE 17 REMAINS CLOSED TO TRAFFIC.

ALL motorists to follow the signed detour.

For the week beginning Monday, June 18, 2018:

Monday thru Sunday:

  • Structural steel to be set in place as the new precast abutments have been set.

Steel to be placed

East abutment

 

 

The following is the anticipated schedule on the I-91 Rockingham Bridges:

Written by on June 8, 2018 in Rockingham Bridges-I91
The following is the anticipated schedule on the I-91 Rockingham Bridges:

For the week beginning Monday, June 11, 2018:

I-91 northbound bridge activities:

Daily I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

At approx.. 8:00am and 11:00am southbound for approximately 30 minutes

At approx.. 10:00am and 2:00pm northbound* for approximately 30 minutes

Please note rolling road block times could vary due to unforeseen circumstances.

*  The northbound rolling road blocks also includes the Exit 6 on ramp.  Motorists may want to detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.

  • Continued beam erection
  • Complete Abutment 1 support walls and remove forms
  • Truck traffic on Golden Hill Road

 

The following is the anticipated schedule for Bridge #8 on VT Route 17:

Written by on June 8, 2018 in BRIDGE 8 VT ROUTE 17

BRIDGE #8 ON VT ROUTE 17 IS CLOSED TO TRAFFIC.

ALL motorists to follow the signed detour.

 

The following is the anticipated work schedule for the week beginning Monday, June 11, 2018. 

It is anticipated the contractor will be working 7 days/week to get this project completed.

Monday thru Sunday:

  • Work continues on the removal of the existing bridge.

The following is the anticipated schedule for VT Route 116:

Written by on June 7, 2018 in Middlebury-Starksboro VT 116

The following is the anticipated work schedule for the week beginning Monday, June 11, 2018:

All work this week will be between East Middlebury/Middlebury to Bristol on VT 116

Monday thru Friday:

  • Continued ditch work.

 Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

The following is the anticipated schedule for VT Route 2A & US 2 project:

The following is the anticipated schedule on Route 2 for the week beginning Monday, June 11, 2018:

Monday thru Friday: Daytime – 6:30am to 7:00pm

  • Drainage work between the Harvest Lane/Blair Park and North Brownell Roads intersections in the westbound lane.

 

Motorist be aware that we are going to try to maintain 2-way traffic at all times however use caution while traveling thru the construction areas.

The following is the anticipated schedule on the I-91 Rockingham Bridges:

Written by on June 1, 2018 in Rockingham Bridges-I91

For the week beginning Monday, June 4, 2018:

Monday thru Friday – Daytime:

  • Continued installing beam support hardware on Piers
  • Continue mobilizing cranes to needed locations
  • Continue receiving beams at the lay-down area
  • Continued preparation to begin beam erection to begin Thursday
  • Continued concrete work on Abutment 1 for support walls
  • Complete backfilling at abutment 2 and construct crane pad
  • Truck traffic on Golden Hill Road

Thursday – I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

  • 8:00am and 11:00am southbound for approximately 30 minutes
  • 10:00am and 2:00pm northbound for approximately 30 minutes

 Friday – I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

  • 8:00am southbound for approximately 30 minutes
  • 10:00am northbound for approximately 30 minutes

The following is the anticipated schedule for Bridge #8 on VT Route 17:

Written by on May 31, 2018 in BRIDGE 8 VT ROUTE 17

The following is the anticipated work schedule for the week beginning Monday, June 04, 2018. 

It is anticipated the contractor will be working 7 days/week to get this project completed.

Monday – 6:00am:

  • BRIDGE WILL BE CLOSED TO THRU TRAFFIC. Newly installed signs will guide motorists along the detour.

Monday thru Sunday:

  • Removal of the existing bridge to begin.
Top