VT 117 – September 25, 2018

Written by on September 24, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • 9:00am Weather permitting, paving to continue from Sand Hill Road westbound to VT-289.
  • 7:00am  Continued structure rehab work around the VT-289 area.
  • 7:00am  Continued culvert work around the Jericho/Richmond town line.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.
 
DRIVE SLOW – USE CAUTION!

VT 117 – September 22, 2018

Written by on September 21, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Weather permitting, paving to begin at the Essex/Jericho town line working westbound.
  • Underdrain work continues between the Jericho/Richmond town line and the US Route 2 intersection.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.
 
DRIVE SLOW – USE CAUTION!

VT 117 – September 21, 2018

Written by on September 20, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • 7:00am  Weather permitting, paving to continue between Essex/Jericho town line and Sand Hill Road.
  • 7:00am  Continued structure work within the VT-289 area.
  • 9:00am  Underdrain work continues between the Jericho/Richmond town line and the US Route 2 intersection.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  
Motorists may want to seek alternate routes during peak hours.
 
DRIVE SLOW – USE CAUTION!

VT Route 2A

Written by on September 20, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated work schedule for the week beginning Monday, September 24, 2018:

Monday thru Wednesday:

  • Continued work on the installation of the pedestrian crosswalk at Bittersweet Circle to include the installation of the flashing beacon signals.

 Wednesday thru Friday:

  • Installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic during this work.

 Motorists should expect minimal delays and use caution while traveling thru the work zone.

The anticipated work schedule for VT Route 116

Written by on September 20, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, September 24, 2018:

Monday thru Friday:

  • Continued pepping side roads and driveway tie-ins in preparation of final paving from Bristol proceeding south to the end of the project limits in Middlebury.

Wednesday thru Saturday:

  • Weather permitting, final paving to begin south of Bristol Village to East Middlebury.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

The anticipated work schedule for the I-91 Rockingham Bridges

Written by on September 20, 2018 in Rockingham Bridges-I91

For the week beginning Monday, September 24 , 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am:
Monday thru Friday – Daytime:

  • Continue installation of bridge deck form work and overhang.
  • Begin installing deck steel reinforcement.
  • Complete removal of temporary supports that held the beams and forms.
  • Remove back wall forms at the northern abutment.
  • Begin forming back wall at the southern abutment.

REED & REED WILL CONTINUE WORKING A NIGHT SHIFT.

VT 117 – September 20, 2018

Written by on September 19, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • 8:00am  Weather permitting, paving to begin at the Essex/Jericho town line working westbound.
  • 9:00am  Underdrain work continues between the Jericho/Richmond town line and the US Route 2 intersection.
  • 7:00am  Continued structure work within the VT-289 area.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.
 
DRIVE SLOW – USE CAUTION!

VT 117 – September 19, 2018

Written by on September 18, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Shoulder/Ditch work continues between the Essex/Jericho town line and N. Williston Road.
  • Underdrain & culvert work continues between the Jericho/Richmond town line and the US Route 2 intersection.
  • Continued structure work within the VT-289 area.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.
 
DRIVE SLOW – USE CAUTION!

Route 2A

Written by on September 17, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

In addition to the anticipated work scheduled for this week:

  • Work has begun on the installation of the new pedestrian crosswalk at Bittersweet Circle.

VT 117 – September 18, 2018

Written by on September 17, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Shoulder/Ditch work continues between the Essex/Jericho town line and Barber Farm Road.
  • Underdrain work continues between the Jericho/Richmond town line and the US Route 2 intersection.
  • Continued installation of cold mix in the N. Williston Road intersection.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.
 
DRIVE SLOW – USE CAUTION!