Middlebury-Starksboro VT 116

 

This project extends along VT 116 for approximately 20 miles from just south of Robinson School in Starksboro to the US 7/VT 116 intersection in Middlebury.  Paving within Bristol Village is not included in this project.

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE CONSTRUCTION ZONE!

Anyone with questions or concerns regarding this project may contact Stephanie Barrett, Public Outreach Coordinator at 802-862-6085.

If you would like to receive a weekly update of the contractors anticipated work schedule, please email [email protected] your request.

PUT YOUR CELL PHONE DOWN!

IT IS AGAINST THE LAW TO USE HAND HELD DEVICES WHILE DRIVING. IF CAUGHT, YOU WILL BE FINED AND 2 POINTS GO ON YOUR LICENSE!

The anticipated work schedule on VT 116

Written by on November 15, 2018 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning Monday, November 19, 2018:

Monday thru Friday:

  • Weather permitting, continue driveway tie-ins between Bristol Notch Road and RT17/116 intersection.
  • Weather permitting, pavement markings to include side road and crosswalks.
  • Placement of shoulder aggregate throughout the project limits.
  • General cleanup work throughout the project limits.

Thursday & Friday:

  • No work due to the Thanksgiving Day holiday


Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

The anticipated work schedule on VT 116

Written by on November 8, 2018 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning Monday, November 12, 2018:

Monday thru Friday:

  • Weather permitting, continue final paving from approximately VT 17/116 intersection proceeding north.
  • Weather permitting, continued paving abutting side roads from approximately Bristol Notch Road proceeding north.
  • Weather permitting, continued driveway aprons from approximately Mead Lane proceeding north.
  • General cleanup work throughout the project limits.


Thursday & Friday:

  • Begin shoulder gravel throughout the project limits.


Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

We ask motorists to use extreme caution while traveling through the work zone.  The safety of the workers, pedestrians and the motorists are of the utmost importance.

The anticipated work schedule on VT 116

Written by on November 8, 2018 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning Monday, November 05, 2018:

Monday thru Friday:

  • Weather permitting, continue final paving from Notch Road, Bristol to Airport Drive, Bristol.
  • Weather permitting, paving abutting side roads & driveway aprons throughout the project.

Wednesday thru Friday:

  • Weather permitting, begin pavement markings throughout the project limits.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

The anticipated work schedule on VT 116:

Written by on October 25, 2018 in Middlebury-Starksboro VT 116

The work schedule for the week beginning Saturday, October 27, 2018:

Saturday thru Friday:

  • Weather permitting, continue paving from Cobble Road, Bristol to the Bristol Village line.
  • Weather permitting, paving abutting side roads & driveway aprons beginning in East Middlebury and proceeding north.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

The anticipated work schedule on VT 116

Written by on October 18, 2018 in Middlebury-Starksboro VT 116

The work schedule for the week beginning Saturday, October 20, 2018:

Saturday thru Friday:

  • Weather permitting, continued paving from East Middlebury to Bristol.

Wednesday thru Friday:

  • Weather permitting, continued paving abutting driveway tie-ins beginning in East Middlebury and proceeding north to Bristol.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

The anticipated work schedule on VT 116:

Written by on October 11, 2018 in Middlebury-Starksboro VT 116

The work schedule for the week beginning Monday, October 15, 2018:

Monday thru Saturday:

  • Weather permitting, paving from East Middlebury to Bristol.

Wednesday thru Saturday:

  • Weather permitting, paving abutting driveway tie-ins beginning in East Middlebury and proceeding north to Bristol.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

The anticipated work schedule for VT Route 116

Written by on October 4, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, October 08, 2018:

Monday:

  • No work due to the Columbus Day holiday.

Tuesday thru Saturday:

  • Weather permitting, final paving to begin south of Bristol Village to East Middlebury.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

Middlebury-Starksboro VT 116

Written by on September 27, 2018 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning Monday, October 01, 2018:

 

Monday thru Friday:

  • There is no work schedule on this project next week.

The anticipated work schedule for VT Route 116

Written by on September 20, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, September 24, 2018:

Monday thru Friday:

  • Continued pepping side roads and driveway tie-ins in preparation of final paving from Bristol proceeding south to the end of the project limits in Middlebury.

Wednesday thru Saturday:

  • Weather permitting, final paving to begin south of Bristol Village to East Middlebury.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

The anticipated schedule for VT Route 116

Written by on September 13, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, September 17, 2018:

Monday:  No work scheduled

Tuesday thru Friday:

  • Prepping side roads and driveway tie-ins in preparation of final paving from Bristol proceeding south to the end of the project limits in Middlebury.

Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.