South Burlington-Williston US Route 2 and VT Route 2A

So. Burlington-Williston RT’S 2&2A

So. Burlington-Williston RT’S 2&2A

This VTrans rehabilitation project is US Route 2 from Boxwood Lane, Williston to Millham Court, So. Burlington along with the repaving project of VT Route 2A from Hurricane Lane to Helena Drive, Williston.

For a complete project overview please click the following link

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE CONSTRUCTION ZONE!

The hours of operations are 7:00pm to 6:00am throughout the project.


The following is the anticipated schedule on US Route 2 for the week beginning Sunday, July 23, 2017.

Sunday – Monday:

  • Milling to begin from the Williston/So. Burlington line to Shunpike Road (Segment #2).
  • Erosion control measures installed in Segment #2.

Monday & Wednesday:

  • Excavation and new sub base material installed in Segment #2.

Wednesday & Thursday:

  • Fine grading in anticipation of paving in Segment #2.

Thursday (& Friday-if necessary):

  • Paving base in Segment #2.

SPECIFIC DAILY UPDATES

Tonight, July 20:

  • Paving from the N/S Brownell Road intersection to┬áMunson Way.
  • Erosion control measures to be installed between the So. Burlington/Williston Town line and Shunpike Road.

MOTORIST SHOULD EXPECT DELAYS as traffic control continues allowing for 1 lane of alternating traffic within the construction zone.


Please note that there may be some daytime maintenance work that needs to be done to keep the roadway in a safe traveling condition.


Traffic control will be present allowing for one lane of alternating traffic.  Motorists should expect delays.

PUT YOUR CELL PHONE DOWN!

IT IS AGAINST THE LAW TO USE HAND HELD DEVICES WHILE DRIVING. IF CAUGHT, YOU WILL BE FINED AND 2 POINTS GO ON YOUR LICENSE!

 

 

 