VT 117 – July 26, 2018

The anticipated work schedule is as follows:

  • Continued shoulder cleanup work within the VT 289 area.
  • Continued underdrain work will continue just east of Barber Farm Road, Jericho.
  • Begin reclaiming the roadway from the Essex/Jericho Town line proceeding westbound. Reclaim takes 10″ of the road surface and basically rototills it and places it back as a gravel surface, recycling the existing material.
Continued roadway maintenance as needed.
 
SLOW DOWN FOR ROUGH ROAD CONDITIONS!
EXPECT DELAYS DURING PEAK HOURS!

Friday, June 29, 2018 on VT 117

The anticipated construction activities (weather permitting) are as follows:

  • Prepping and paving the milled surface within the VT-289 on/off ramps.
  • Continued underdrain work between N. Williston Road and the Essex/Jericho town line.

Motorists may choose to seek alternate routes as they can expect delays during peak hours. Traffic control will be present allowing for 1-lane of alternating traffic within the construction zones.

1st beam to northbound abutment

Written by on June 21, 2018 in Rockingham Bridges-I91, Uncategorized
1st beam to northbound abutment

BRIDGE 8 VT ROUTE 17 Fact Sheet

Written by on October 1, 2017 in Uncategorized
BRIDGE 8 VT ROUTE 17 Fact Sheet