I-91 Rockingham Bridges – 10/7/21

Written by on October 7, 2021 in Rockingham Bridges I-91


The following is an update of the construction to take place for the week beginning October 11, 2021.

Monday:

  • No work due to the Indigenous People’s Day holiday

Tuesday:

  • Weather permitting, paving of the U-Turns

Tuesday through Friday 6:00 a.m. to 5:00 p.m.:

  • General cleanup work throughout the project
  • Continue demobilization
View looking north from the I-91 U-Turn
DAILY LANE CLOSURES  –  REDUCED SPEEDS  –  USE CAUTION!

Follow us on FacebookFollow us on Twitter (#91rockbridges)

Subscribe

If you enjoyed this article, subscribe now to receive more just like it.

Subscribe via RSS Feed

Comments are closed.