Rockingham Bridges I-91 06/10/21

Written by on June 10, 2021 in Rockingham Bridges I-91

********* ADVANCED DETOUR NOTIFICATION **********

On Monday, June 21, 2021 at 7:00 a.m. the Exit 6 southbound off-ramp will be closed for the week to allow for milling and paving of the ramp. The ramp is expected to reopen on Friday, June 25, 2021 by 5:00 p.m.
All motorists wanting to use Exit 6 southbound off-ramp will be detoured to Exit 7 southbound off-ramp, then follow a signed detour on Route 5 southbound.

The following is an update of the construction to take place for the week beginning June 14, 2021. Monday through Friday 6:00 a.m. to 5:00 p.m.:

  • Begin shoulder work
  • Continue work on removal of trestle components
  • Continue with various “punch list” items
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Follow us on Facebook; Follow us on Twitter (#91rockbridges),  Live Traffic Camera

Subscribe

If you enjoyed this article, subscribe now to receive more just like it.

Subscribe via RSS Feed

Comments are closed.

Top