Rockingham Bridges I-91

Written by on December 6, 2018 in Rockingham Bridges-I91, Uncategorized

The following is the anticipated work schedule for the week beginning Monday, December 10, 2018:

I-91 northbound bridge activities:

Monday thru Friday – 7:00am to 5:00pm:

  • Continue placement of the concrete barriers on the bridge
  • Continue maintenance of traffic control devices, due to weather


I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!