The following is the anticipated work schedule for the week beginning Monday, October 08, 2018.

 I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:

  • Begin construction on the northbound abutment approach.
  • Begin placing concrete deck segments.
  • Continue installation deck reinforcing.
  • Complete forming back wall at the southern abutment.