The following is the anticipated work schedule for the week beginning Monday, October 15, 2018:

I-91 northbound bridge activities:        

Monday thru Thursday – 5:00pm to
Monday thru Friday – Daytime:

  • Continue placing concrete deck segments.
  • Complete installation deck reinforcing.
  • Complete approach road work up to the approach slab area.
  • Begin forming the approach slabs.
  • Begin installation of reinforcement for the barrier curb.

Please drive slow and use caution while traveling thru the work zone.