Rockingham Bridges I-91

Written by on May 23, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, May 27, 2019:

Monday:

No work due to the Memorial Day Holiday!

Tuesday thru Friday:

  • Work continues on the installation of the southbound crossover to include paving, shoulders & line striping.
  • Work continues on SB Piers #2 & #3.
  • Prep work on the existing southbound bridge for start of demolition
  • Installation of the southbound traffic control devises. 

REMINDERS:

  • JUNE 04, 2019 at 9:30am there will be a rolling roadblock for southbound motorists in preparation of opening the southbound crossover.  Motorists can anticipate approximately a 20-minute delay in their travels. If time does not allow for all work to be completed within the 20 minutes, there will be another rolling roadblock at 11:00am for approximately another 20-minute delay.
  • JUNE 4, 2019 THRU JUNE 6, 2019 the EXIT 6 SOUTHBOUND OFF-RAMP WILL BE CLOSED AT 9:30am June 4, 2019 until the end of the workday June 6, 2019.  Motorists will be detoured using Exit 7 Off-Ramp then follow the signed detour on Route 5 southbound.  All trucks over 14’ high will follow a signed detoured using Route 11.

KEEP YOUR HEADS UP AND YOUR CELL PHONE DOWN!