Below is the anticipated work schedule for the week beginning Monday, June 03, 2019:

Monday thru Friday:

  • Preparation work for demolition of SB Pier #1.
  • Work continues on SB Piers #2 & #3.
  • Begin removal of the existing southbound bridge deck
  • Installation of the southbound traffic control devises. 

TUESDAY:

  • 9:30am there will be a rolling roadblock for southbound motorists in preparation of opening the southbound crossover.  Motorists can anticipate approximately a 20-minute delay in their travels. If time does not allow for all work to be completed within the 20 minutes, there will be another rolling roadblock at 11:00am for approximately another 20-minute delay.

TUESDAY THRU THURSDAY:

  • EXIT 6 SOUTHBOUND OFF-RAMP WILL BE CLOSED AT 9:30am June 4, 2019 until the end of the workday June 6, 2019.  Motorists will be detoured using Exit 7 Off-Ramp then follow the signed detour on Route 5 southbound.  All trucks over 14’ high will follow a signed detoured using Route 11.

KEEP YOUR HEADS UP AND YOUR CELL PHONE DOWN!