Rockingham Bridges I-91

Written by on August 1, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, August 5, 2019:

Southbound I-91 bridge activities:

Monday through Friday:

  • Nighttime activity is done until further notice
  • Continue substructure removal
  • Continue placing Pier 3 shaft section 3
  • Continue Pier 2 shaft work
  • Grade work on the northbound abutment
  • Demolition of the southbound abutment
  • Continue maintenance of traffic control devises.