Below is the anticipated work schedule for the week beginning Tuesday, September 03, 2019:

Southbound I-91 bridge activities:

Tuesday through Friday:

  • Continue Pier 3 cap forms
  • Form and place Pier 2 section 4
  • Work continues on each abutment approaches
  • Demolition of the existing southbound Pier 3
  • Continue work at the new Pier 1
  • Continue maintenance of traffic control devises.