Below is the anticipated work schedule for the week beginning Monday, September 09, 2019:

Southbound I-91 bridge activities:

Monday through Friday:

  • Continue Pier 3 cap work
  • Continue work on Pier 2
  • Grading at northbound abutment (#2) approach and begin form work
  • Work continues on the southbound abutment (#2) approach
  • Continue demolition of the existing southbound Pier 3 causing late work activities
  • Continue work at the new Pier 1 site
  • Continue maintenance of traffic control devises.