Rockingham Bridges I-91

Written by on October 25, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, October 29, 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:

  • Continue work on both approaches.
  • Continue curing of the concrete deck placements.
  • Continue placement of the barrier curb.

Please use caution while traveling thru the work zone.

Curing Concrete

Curing Concrete