The following is an update of the construction to take place for the week beginning Sunday, July 12, 2020.

Southbound I-91 bridge activities resume with limited personnel.

Sunday through Friday- 24 hours/day:

  • Bridge deck work to continue
  • Placement of concrete and other work at the northbound abutment
  • Tree branch trimming within the construction zone on I-91
  • Maintenance of traffic control devices continues

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.