The anticipated work on VT 117 for the week beginning August 12, 2019

ALL WORK THIS WEEK IS EXPECTED TO BE THROUGHOUT THE PROJECT LIMITS.

Monday and Tuesday:

  • Continue milling the approaches on each end of the project along with all side road approaches

Wednesday through Friday:

  • Driveway paving preparation work

Monday through Friday:

  • Shoulder clean up and ditch work

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

MOTORISTS, PLEASE SLOW DOWN!  SAFETY FIRST!