The anticipated work schedule on VT 116:

Written by on October 25, 2018 in Middlebury-Starksboro VT 116

The work schedule for the week beginning Saturday, October 27, 2018:

Saturday thru Friday:

  • Weather permitting, continue paving from Cobble Road, Bristol to the Bristol Village line.
  • Weather permitting, paving abutting side roads & driveway aprons beginning in East Middlebury and proceeding north.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.