The following is the anticipated schedule for Bridge #8:

Written by on August 2, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, August 06, 2018:

 Monday thru Friday:

  • Removal of old concrete piers
  • Installation of bridge plug joints
  • General cleanup work throughout

Motorists should be aware on Monday there will be traffic control allowing for one lane of alternating traffic.

There will be 2 lanes of traffic open during Addison County Field Days.