The following is the anticipated schedule for Bridge #8:

Written by on August 16, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, August 20, 2018:

Monday thru Friday:

  • Continued removal of old concrete pier
  • If time allows, begin causeway removal
  • General cleanup work throughout 

There should be minimal impact on traffic.