VT 117 – August 09, 2018

The anticipated work activities are as follows:

  • Continued removal of unsuitable material and backfilling with new material to proper grade from VT-289 off ramp to Tiffany Lane.
  • Continued culvert work near the Essex/Jericho town line.
  • Slope stabilization work continues within the Skunk Hollow Road area.

Continued road maintenance as needed.