The anticipated work activities are as follows:

  • Continued removal of unsuitable material and backfilling with new material to proper grade from the Essex/Jericho town line to Sand HIll Road.
  • Continued culvert work approximately 500′ from Tiffany Lane.
  • Slope stabilization work continues within the Skunk Hollow Road area.

Continued road maintenance as needed.