VT Route 2A – Williston

Written by on October 10, 2019 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated daytime work schedule for the week beginning Monday, October 14, 2019.  

Monday – No work due to the Columbus Day holiday

Tuesday through Friday – 7:00 a.m. to 5:30 p.m.:

  • Continue ditch and shoulder work south of Morgan Parkway
  • Continue widening work on James Brown Drive

Tuesday and Wednesday (Wed. if necessary) – 7:00 a.m. to 5:30 p.m.:

  • Paving the widened area from Morgan Parkway south to River Cove Road. Traffic control will be present at Morgan Parkway.

Motorists should have minimal affect by this work.  Two-way traffic will be maintained.  Pedestrians will be detoured around the work area.

Wednesday and Thursday – 7:00 p.m. to 6:00 a.m.:

  • Milling (grinding) the existing roadway from the bridge to River Cove Road

Traffic control will be present allowing for one-lane of alternating traffic within the work area. Motorists should plan for delays.

   Please use caution while traveling thru the work zone.