VT Route 2A – Williston

Written by on October 17, 2019 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated daytime work schedule for the week beginning Monday, October 21, 2019:

Monday through Friday:

  • Continue ditch and shoulder work
  • Continue widening work on James Brown Drive
  • Curb and structure work around Morgan Parkway
  • General cleanup work in anticipation of winter shut down

Monday and Tuesday: – 7:00 a.m. to 5:30 p.m.:

  • Weather permitting, shoulder paving along Route 2A

Motorists should expect minimal delays.  Two-way traffic will be maintained.  Pedestrians will be detoured around the work area.