VT Route 2A – Williston

Written by on November 21, 2019 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated daytime work schedule for the week beginning Monday, November 21, 2019:

Monday and Tuesday:

  • Installation of street lighting within the James Brown Drive intersection
  • Minor work to the signal system

Wednesday through Friday:

  • No work due to the Thanksgiving Day holiday

Motorists should have minimal affect by this work.  Two-way traffic will be maintained. 