VT Route 2A – Williston

Written by on May 14, 2020 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated daytime work schedule for the week beginning Saturday, May 16, 2020:

Saturday – 6:00 a.m. to 5:00 p.m.:

  • Continue sidewalk construction on the east side between Morgan Parkway and Eastview Circle
  • Weather permitting, continue paving the leveling course

Sunday – 4:00 p.m. to 12:00 a.m.:

  • Catch basin adjustments throughout the project in anticipation of final paving

Tuesday through Thursday (possibly Friday) – 6:00 p.m. to 6:00 a.m.:

  • Weather permitting, final paving of the wearing course

Monday through Friday – 6:00 a.m. to 5:30 p.m.:

  • Work at the River Cove Road intersection
  • Completion of the sidewalk construction on the east side between Morgan Parkway and Eastview Circle
  • Installation of topsoil along the shoulders

Traffic control will be present during all activities allowing for one lane of alternating traffic.  Motorists may encounter minor delays.