Archive for May, 2017

VT 116/Hinesburg Road Culvert Replacement

Written by on May 19, 2017 in ZArchives
VT 116/Hinesburg Road Culvert Replacement

 

The Vermont Agency of Transportation in conjunction with CCS Constructors, Inc. will begin the culvert replacement on VT Route 116/Hinesburg Road at Potash Brook.  The anticipated start date June 05, 2017 with a completion date of September 01, 2017.

This project will cause Hinesburg Road/VT Route 116 to be closed to thru traffic between Williston Road and Kennedy Drive beginning in mid to late June 2017.  Pedestrians/bicycles will still have the ability to cross the construction site via a temporary bridge.

 

 

 


VT ROUTE 116/HINESBURG ROAD IS OPEN TO THRU TRAFFIC

The following is the anticipated schedule on VT Route 116/Hinesburg Road for the week beginning November 27, 2017:

 Monday thru Friday – 7:00am to 5:00pm:

  • Landscaping work continues within the construction zone well off the road.

Motorists should not encounter delays.

 


The following is the anticipated schedule on VT Route 116/Hinesburg Road for the week beginning Monday, December 04, 2017.

Monday thru Friday – Daytime:

  • Weather permitting, landscaping work within the construction zone well off the roadway continues.

Motorists should not encounter any delays.

This will be the final update for the 2017 construction season.  There will be some tree & shrub plantings next sprint to finalize the project which should have minor impact (lane closures) on the traveling public.

 

I-89 Colchester-Swanton

Written by on May 1, 2017 in ZArchives
I-89 Colchester-Swanton

PUT YOUR CELL PHONE DOWN!

IT IS AGAINST THE LAW TO USE HAND HELD DEVICES WHILE DRIVING. IF CAUGHT, YOU WILL BE FINED AND 4 POINTS GO ON YOUR LICENSE!


This paving project is complete.

The Vermont Agency of Transportation along with myself would like to thank the traveling public and all parties affected for their patience and understanding during the construction period.

Please note that there is a couple of other projects on I-89 around the Milton Area that is completely separate from this project.


Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Information Officer at 802-862-6085.  If you would like to receive a weekly update of the contractors anticipated work schedule please email [email protected] your request.

Top