The following is the anticipated work schedule for the week beginning Saturday, September 29, 2018:
Saturday, Monday & Tuesday:
- Weather permitting, completion of base course paving from Sand Hill Road to Tiffany Lane.
Monday thru Friday:
- Culvert work continues from the Essex/Jericho town line to the US Route 2 intersection.
- Structure rehabilitation work continues within the VT-289 intersection to Tiffany Lane.
- Shoulder work from Tiffany Lane to the Essex/Jericho town line.
- Continued guardrail work between the Essex/Jericho town line and Tiffany Lane.
- Weather permitting, paving within the VT-289 intersection.
COMMUTING MOTORISTS SHOULD SEEK ALTERNATE ROUTES. EXPECT DELAYS DURING PEAK HOURS!
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
The following is the anticipated work schedule for the week beginning Monday, October 01, 2018:
Monday thru Friday:
- Final work on the installation of the pedestrian crosswalk at Bittersweet Circle to include pavement markings.
Monday thru Wednesday:
- Installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic on Eastview during this work.
Motorists should expect minimal delays and use caution while traveling thru the work zone.
The anticipated work schedule is as follows:
- 9:00am Weather permitting, paving to continue from Sand Hill Road to Valley View Road.
- 7:00am Continued structure rehab work around the VT-289 area.
- 7:00am Continued culvert work around the Jericho/Richmond town line.
- 7:00am Guardrail work will continue between N. Williston Road and the Essex/Jericho town line.
Traffic control will be present allowing for one lane of alternating traffic through the work zones. Motorists expect delays!
DRIVE SLOW – USE CAUTION!
The following is the anticipated work schedule for the week beginning Monday, October 01, 2018.
I-91 northbound bridge activities:
Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:
• Continue installation of bridge deck prep and overhang.
• Remove back wall forms at the northern abutment.
• Continue forming back wall at the southern abutment.
Please drive slow & use caution thru the work zone.
The anticipated work schedule is as follows:
- 9:00am Weather permitting, paving to continue from Sand Hill Road westbound towards Tiffany Lane.
- 7:00am Continued structure rehab work around the VT-289 area.
- 7:00am Continued culvert work around the Jericho/Richmond town line.
- 7:00am Guardrail work will continue between N. Williston Road and the Essex/Jericho town line.
Traffic control will be present allowing for one lane of alternating traffic through the work zones. Motorists expect delays!
DRIVE SLOW – USE CAUTION!
The anticipated work schedule is as follows:
- 9:00am Weather permitting, paving to continue from Sand Hill Road westbound towards Tiffany Lane.
- 7:00am Continued structure rehab work around the VT-289 area.
- 7:00am Continued culvert work around the Jericho/Richmond town line.
- 7:00am Guardrail work begins between the Essex/Jericho town line and Sand Hill Road.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.
DRIVE SLOW – USE CAUTION!
The anticipated work schedule is as follows:
- 9:00am Weather permitting, paving to continue from Sand Hill Road westbound to VT-289.
- 7:00am Continued structure rehab work around the VT-289 area.
- 7:00am Continued culvert work around the Jericho/Richmond town line.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.
DRIVE SLOW – USE CAUTION!
The anticipated work schedule is as follows:
- Weather permitting, paving to begin at the Essex/Jericho town line working westbound.
- Underdrain work continues between the Jericho/Richmond town line and the US Route 2 intersection.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.
DRIVE SLOW – USE CAUTION!
The anticipated work schedule is as follows:
- 7:00am Weather permitting, paving to continue between Essex/Jericho town line and Sand Hill Road.
- 7:00am Continued structure work within the VT-289 area.
- 9:00am Underdrain work continues between the Jericho/Richmond town line and the US Route 2 intersection.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.
Motorists may want to seek alternate routes during peak hours.
DRIVE SLOW – USE CAUTION!