Archive for September, 2018
The anticipated work schedule is as follows:
- Weather permitting, continued installation of cold mix between Sand Hill Road and Tiffany Lane.
- Shoulder clean up and ditch work continues between the Essex/Jericho town line and N. Williston Road.
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
Commuting motorists should seek alternate routes. Expect delays during peak hours!
For the week beginning Monday, September 17, 2018:
Monday: No work scheduled
Tuesday thru Friday:
- Prepping side roads and driveway tie-ins in preparation of final paving from Bristol proceeding south to the end of the project limits in Middlebury.
Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.
The anticipated work schedule is as follows:
Motorists should expect long delays between 2pm & 7pm between N. Williston Road and Sand Hill Road
- Weather permitting, continued installation of cold mix between the Essex/Jericho town line and Sand Hill Road.
- Shoulder clean up and ditch work continues between Valley View Drive and Tiffany Lane.
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
Commuting motorists should seek alternate routes. Expect delays during peak hours!
The anticipated work schedule is as follows:
Motorists should expect long delays between 2pm & 7pm between N. Williston Road and Sand Hill Road
- Weather permitting, continued installation of cold mix between the Essex/Jericho town line and Sand Hill Road.
- Underdrain work continues between Barber Farm Road and the Jericho/Richmond town line.
- Shoulder clean up and ditch work continues between Valley View Drive and Tiffany Lane.
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
Commuting motorists should seek alternate routes. Expect delays during peak hours!
The anticipated work schedule is as follows:
- Underdrain work continues between Barber Farm Road and the Jericho/Richmond town line.
- Slope stabilization work continues near the VT-117 & US Route 2 intersection.
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
Commuting motorists should seek alternate routes. Expect delays!
For the week beginning Saturday, September 08, 2018:
Saturday:
- Weather permitting & tentatively, continued installation of cold mix from the Essex/Jericho town line proceeding west to Tiffany Lane.
Monday thru Friday:
- Weather permitting, continued installation of cold mix from the Essex/Jericho town line proceeding west to Tiffany Lane.
- Underdrain and slope stabilization work continues between Barber Farm Road and the US Route 2 intersection.
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
Commuting motorists should seek alternate routes. Expect delays during peak hours!
The work schedule for Friday, September 07, 2018 is as follows:
- Continued underdrain and slope stabilization work between Barber Farm Road and the Jericho/Richmond town line.
- Shoulder cleanup between VT-289 and Tiffany Lane.
Traffic control is present allowing for one lane of alternating travel.
USE CAUTION – DRIVE SLOW!