Archive for November, 2018

Rockingham Bridges I-91

Written by on November 29, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, December 03, 2018:

********* IMPORTANT NOTIFICATION *********

Due to the unfortunate timing of winter rolling in, we will not be able to complete the driving surface of the northbound bridge this 2018 construction season, as anticipated.  The traffic pattern will remain as it has been during the construction of the northbound bridge until Spring 2019 when the temperatures allow for paving the new bridge deck and approaches. 

Construction activities will continue thru the winter and I will continue sending you notifications unless otherwise stated.

************************************************

I-91 northbound bridge activities:

Monday thru Friday – 7:00am to 5:00pm:

  • Continue placement of the concrete barriers on the bridge.
  • Continue maintenance of traffic control devices, due to weather


I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!

The anticipated work schedule on VT 116

Written by on November 29, 2018 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning Monday, December 03, 2018:

Monday thru Friday:

  • Weather permitting, continue driveway tie-ins between Bristol Notch Road and RT17/116 intersection.
  • Weather permitting, pavement markings to include side road and crosswalks.
  • Placement of shoulder aggregate throughout the project limits.
  • General cleanup work throughout the project limits.

Please note the contractor will continue to work on the above tasks as weather allows in order to provide a safe roadway for the traveling public.

The anticipated work schedule on VT 117:

Written by on November 29, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The following is the anticipated work schedule for the week beginning Saturday, December 01, 2018 – Please note at this time of the year work can be weather dependent.

Saturday, Monday thru Friday:

  • Weather permitting, removal of the temporary lines between Tiffany Lane and the Essex/Jericho town line and repainting the lines at the correct locations along with other pavement markings. This work is weather dependent and will require the roadway surface to be dry.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

VT 117 – November 30, 2018

Written by on November 29, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The following is the anticipated work schedule:

  • Continued installation of signs
  • Continued installation of delineators at the end of the guardrail runs
  • If weather permits, patching of the culvert crossing in Jericho.

Motorists should expect minor delays.

Please use caution when traveling thru the construction zone.

VT 117 – November 29, 2018

Written by on November 28, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule is as follows:

  • Installation of signs
  • Installation of delineators at the end of the guardrail runs

Motorists should expect minor delays.

Please use caution when traveling thru the construction zone.

 

VT 117 – November 28, 2018

Written by on November 27, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated weather dependent work schedule is as follows:

  • There is no work scheduled.
Motorists should expect minimal impact on traffic.
 
DRIVE SLOW – USE CAUTION!

VT 117 – November 27, 2018

Written by on November 26, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated weather dependent work schedule is as follows:

  • There is no work scheduled due to the weather forecast.
Motorists should expect minimal impact on traffic.
 
DRIVE SLOW – USE CAUTION!

Rockingham Bridges I-91

Written by on November 21, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, November 26, 2018:

********* IMPORTANT NOTIFICATION *********

Due to the unfortunate timing of winter rolling in, we will not be able to complete the driving surface of the northbound bridge this 2018 construction season, as anticipated.  The traffic pattern will remain as it has been during the construction of the northbound bridge until Spring 2019 when the temperatures allow for paving the new bridge deck and approaches. 

Construction activities will continue thru the winter and I will continue sending you notifications unless otherwise stated.

************************************************

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – 7:00am to 5:00pm:

  • Continue placement of the concrete barriers on the bridge.
  • Continue maintenance of traffic control devices, due to weather


I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!

The anticipated work on VT 116

Written by on November 21, 2018 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning Monday, November 26, 2018:

Monday thru Friday:

  • Weather permitting, continue driveway tie-ins throughout the project limits.
  • Weather permitting, continued painting pavement markings to include stop bars and crosswalks.
  • Placement of shoulder aggregate throughout the project limits.
  • General cleanup work throughout the project limits.

 

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

The anticipated work schedule on VT 117

Written by on November 21, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The following is an update to the work schedule for the week beginning Monday, November 26, 2018:

Monday:

  • Continued general clean-up work throughout the project limits.

Tuesday thru Friday:

  • Weather permitting, removal of the temporary lines between Tiffany Lane and the Essex/Jericho town line and repainting the lines at the correct locations along with other pavement markings.
  • Weather permitting, overlay of the line striping between the Essex/Jericho town line to the Route 2/VT 117 intersection.
  • Guardrail work between Tiffany Lane and the Essex/Jericho town line.
  • Signal work at the VT 289 off ramp.


Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

Top