Archive for November, 2018

VT 117 – November 09, 2018

Written by on November 8, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule is as follows:

  • Weather permitting, begin final paving between Greenfield Road and Valleyview Drive.
  • Structure adjustments between VT 289 and Tiffany Lane.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

Rockingham Bridges I-91

Written by on November 8, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, November 12, 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – 7:00am to 5:00pm:

  • Continue work on both bridge approaches.
  • Continue placement of the concrete barriers on the bridge.


I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!

The anticipated work schedule on VT 116

Written by on November 8, 2018 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning Monday, November 12, 2018:

Monday thru Friday:

  • Weather permitting, continue final paving from approximately VT 17/116 intersection proceeding north.
  • Weather permitting, continued paving abutting side roads from approximately Bristol Notch Road proceeding north.
  • Weather permitting, continued driveway aprons from approximately Mead Lane proceeding north.
  • General cleanup work throughout the project limits.


Thursday & Friday:

  • Begin shoulder gravel throughout the project limits.


Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

We ask motorists to use extreme caution while traveling through the work zone.  The safety of the workers, pedestrians and the motorists are of the utmost importance.

The anticipated work schedule on VT 116

Written by on November 8, 2018 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning Monday, November 05, 2018:

Monday thru Friday:

  • Weather permitting, continue final paving from Notch Road, Bristol to Airport Drive, Bristol.
  • Weather permitting, paving abutting side roads & driveway aprons throughout the project.

Wednesday thru Friday:

  • Weather permitting, begin pavement markings throughout the project limits.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

VT 117 – November 08, 2018:

Written by on November 7, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule is as follows:

  • Continued work at the VT 289 off-ramp signal with little impact on the traveling public.
  • Potential structure rehabilitation work between VT 289 and Tiffany Lane.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

VT 117 – November 07, 2018

Written by on November 6, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule is as follows:

  • Continued work at the VT 289 off-ramp.
  • Miscellaneous clean up work at the culvert areas throughout the project.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

VT 117 – November 06, 2018

Written by on November 5, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule is as follows:

  • Continued side road work and driveway prep for final paving between Tiffany Lane and No. Williston Road.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

 

The anticipated work schedule on VT 117

Written by on November 5, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The following is the anticipated work schedule for the week beginning Monday, November 05, 2018 – Please note at this time of the year work can be weather dependent.

Monday thru Wednesday:

  • Side road preparation in anticipation of final paving from the west end of the project in Essex to No. Williston Road.

Monday thru Friday:

  • Continued drainage work and shoulder clean-up between Skunk Hollow Road and US Route 2.

 Wednesday thru Friday:

  • Installation of signal foundation at 289 Off-Ramp and VT 117.

COMMUTING MOTORISTS SHOULD SEEK ALTERNATE ROUTES.  EXPECT DELAYS DURING PEAK HOURS!

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!

VT 117 – November 02, 2018

Written by on November 1, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Shoulder work to continue between VT 289 and the west end of the project in Essex.
  • Miscellaneous pavement patching throughout the project limits.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

Rockingham Bridges I-91

Written by on November 1, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, November 05, 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – 7:00am to 5:00pm:

  • Continue work on both approaches.
  • Continue curing of the concrete deck placements.
  • Continue placement of the barrier curb.

Please use caution while traveling thru the work zone.