Archive for January, 2019
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, January 26, 2019:
Monday thru Friday:
- Continue installation of the southbound Pier #3 cofferdam
- Continue stripping northbound deck overhang form work
- Begin drilling ledge for installation of southbound Pier #2 cofferdam
- Begin installation of retaining wall at southbound Pier #2
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, January 21, 2019:
Monday thru Friday:
- Continue work on the bridge concrete barriers.
- Continue installation of the southbound Pier #3 cofferdam
- Strip northbound deck overhang form work
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule for the week beginning Monday, January 14, 2019:
I-91 northbound bridge activities:
Monday thru Friday:
- Continue placement of the concrete barriers on the bridge
- Continue maintenance of traffic control devices, due to weather
- Begin installation of the southbound Pier #3 cofferdam
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule for the week beginning Monday, January 07, 2019:
I-91 northbound bridge activities:
Monday – Tuesday:
- No work due to the New Year holiday.
Wednesday thru Friday:
- Continue placement of the concrete barriers on the bridge
- Continue maintenance of traffic control devices, due to weather
- Prep for excavation to begin installation of the southbound Pier #3 cofferdam
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!