The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, March 04, 2019:
Monday thru Friday:
- Continue driving “H-Pile” at Pier #3 for ground stabilization
- Continue driving “Sheet Pile” at Pier #2 for ground stabilization
- Continue installation of hangers & conduit under the NB Bridge
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, February 25, 2019:
Monday thru Friday:
- Begin driving “H-Pile” at Pier #3 for ground stabilization
- Begin driving “Sheet Pile” at Pier #2 for ground stabilization
- Continue installation of hangers & conduit under the NB Bridge
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, February 18, 2019:
Monday thru Friday:
- Excavate for the southbound Pier #3 cofferdam
- Continue installation of conduit under the NB Bridge
- Continue drilling ledge for installation of southbound Pier #2 cofferdam
- Excavate at Pier #2 cofferdam to prep for sheet pile installation
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, February 11, 2019:
Monday thru Friday:
- Continue installation of retaining pike for the southbound Pier #3 cofferdam
- Installation of hangers and conduit under the NB Bridge
- Continue drilling ledge for installation of southbound Pier #2 cofferdam
- Continue installation of wind stops on NB Bridge
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, February 04, 2019:
Monday thru Friday:
- Continue installation of the southbound Pier #3 cofferdam
- Continue stripping northbound deck overhang form work
- Continue drilling ledge for installation of southbound Pier #2 cofferdam
- Continue installation of retaining wall at southbound Pier #2
- Repair and install wind stops on NB Bridge
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!