Archive for February, 2020
The following is an update of the construction to take place for the week beginning Monday, March 2 2020.
Southbound I-91 bridge activities:
Monday through Friday:
- Continue girder closures
- Continue work on abutments
- Continue work on the pier footers
- Continue maintenance of traffic control devises
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, February 24, 2020.
Southbound I-91 bridge activities:
Saturday (weather permitting), Monday through Friday:
- Continue girder closures
- Continue work on abutments
- Continue work on the pier footers
- Continue maintenance of traffic control devises
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Saturday, February 15, 2020.
Southbound I-91 bridge activities:
Saturday (weather permitting), Monday through Friday:
- Continue girder closures
- Demolition of the old northbound Pier 2 footer
- Continue maintenance of traffic control devises
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Saturday, February 8, 2020.
Southbound I-91 bridge activities:
Saturday (weather permitting), Monday through Friday:
- Continue girder closures
- Demolition of the old northbound Pier 2 footer
- Continue maintenance of traffic control devises
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
Connect