Archive for March, 2020

Rockingham Bridges I-91

Written by on March 12, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, March 16, 2020.

Southbound I-91 bridge activities will be suspended after work tomorrow Friday, March 13, 2020 as the contractor will be shutting down until mid-April for the final phase of construction.  Minimal personnel will continue to be onsite during this shut-down period.I will resume these weekly updates prior to work resuming in full capacity.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on March 5, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, March 9, 2020.

Southbound I-91 bridge activities:

Monday through Friday:

  • Continue girder closures
  • Mobilization of equipment to Golden Hill Road
  • Continue maintenance of traffic control devises

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Top