Archive for September, 2020

Rockingham Bridges I-91

Written by on September 17, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91


The following is an update of the construction to take place for the week beginning Monday, September 21, 2020.

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues to include tying in deck steel
  • Continue work on the approach slab at the northbound abutment
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on September 10, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91


The following is an update of the construction to take place for the week beginning Monday, September 14, 2020.

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues to include tying in deck steel
  • Continue backfilling and forming southbound abutment
  • Placement of concrete in the approach slab at the northbound abutment
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on September 3, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91


The following is an update of the construction to take place for the week beginning Monday, September 7, 2020.

Monday:  No work due to the Labor Day holiday

Tuesday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues including pouring of the first concrete section
  • Backfilling at the southbound abutment
  • Forming the approach at the northbound abutment
  • Maintenance of traffic control devices continues

NARROW LANES – REDUCED SPEEDS – USE CAUTION!