Archive for December, 2020

Rockingham Bridges I-91

Written by on December 30, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, January 4, 2021.

Monday through Friday – 6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues. Motorists should be aware of trucks entering/exiting the construction zone.
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on December 23, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, December 28, 2020.

Monday through Wednesday – 6:00 a.m. to 5:00 p.m., Thursday – 6:00 a.m. to noon;  Friday:  No work due to the New Year holiday

  • Bridge deck work continues. Motorists should be aware of concrete trucks entering/exiting the construction zone.
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on December 17, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, December 21, 2020.

Monday through Wednesday – 6:00 a.m. to 5:00 p.m., Thursday – 6:00 a.m. to noon;  Friday:  No work due to the Christmas holiday

  • Bridge deck work continues. Motorists should be aware of concrete trucks entering/exiting the construction zone.
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on December 10, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, December 14, 2020.

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues. Motorists should be aware of concrete trucks entering/exiting the construction zone.
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on December 3, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, December 7, 2020.

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!