The following is the anticipated work schedule for the week beginning Saturday, September 29, 2018:
Saturday, Monday & Tuesday:
- Weather permitting, completion of base course paving from Sand Hill Road to Tiffany Lane.
Monday thru Friday:
- Culvert work continues from the Essex/Jericho town line to the US Route 2 intersection.
- Structure rehabilitation work continues within the VT-289 intersection to Tiffany Lane.
- Shoulder work from Tiffany Lane to the Essex/Jericho town line.
- Continued guardrail work between the Essex/Jericho town line and Tiffany Lane.
- Weather permitting, paving within the VT-289 intersection.