The following work schedule on VT 117 for the week beginning Saturday, October 5, 2019

Written by on October 3, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

Saturday, Monday through Friday:

  • Weather permitting, continue pavement markings
  • Continue sign installation
  • Continue mailbox adjustments
  • General cleanup work

Monday:

  • Completion of shoulder work

Tuesday & Wednesday:

  • Weather permitting, completion of paving driveway tie-ins.

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

PLEASE SLOW DOWN!  SAFETY FIRST!

The anticipated work schedule for VT 117 on October 4, 2019

Written by on October 3, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, pavement markings throughout the project limits
  • Continue shoulder work throughout the project limits
  • Continue sign installation
  • Mailbox adjustments throughout the project limits
  • General cleanup work throughout the project limits

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zone.

Rockingham Bridges I-91

Written by on October 3, 2019 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Saturday, October 5, 2019

Southbound I-91 bridge activities:

Saturday, Monday through Friday:

  • Continue work on Pier 2 for cap placement
  • Continue form work for placing shaft 1 at Pier 1
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Continue maintenance of traffic control devises.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

VT Route 2A – Williston

Written by on October 3, 2019 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated daytime work schedule for the week beginning Monday, October 7, 2019.  

Monday through Friday – 7:00 a.m. to 5:30 p.m.:

  • Continue ditch and shoulder work south of Morgan Parkway
  • Widening work on James Brown Drive – flaggers will be present

Motorists should have minimal affect by this work.  Two-way traffic will be maintained.  Pedestrians will be detoured around the work area.

Monday through Friday – 7:00 p.m. to 6:00 a.m.:

  • It is in hopes that night work will not be necessary (providing the 2A widening gets completed tonight & tomorrow night 10/3& 10/4) .  If necessary, widening work will continue and Traffic control will be present allowing for one-lane of alternating traffic within the work area. Motorists should plan for delays.

Traffic control will be present allowing for one-lane of alternating traffic within the work area. Motorists should plan for delays.

   Please use caution while traveling thru the work zone.

The anticipated work schedule on VT 117 for October 3, 2019

Written by on October 2, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, pavement markings throughout the project limits
  • Continue shoulder work throughout the project limits
  • Continue sign installation
  • Mailbox adjustments throughout the project limits
  • General cleanup work throughout the project limits

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zone.

The anticipated work schedule for VT 117 on October 2, 2019

Written by on October 1, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, completion of driveway tie-ins.
  • Continue shoulder work throughout the project limits
  • General cleanup work throughout the project limits

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

The anticipated work schedule on VT 117 for October 1, 2019

Written by on October 1, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue paving abutting side roads and driveway tie-ins.
  • Continue shoulder work throughout the project limits
  • Weather permitting, pavement markings throughout the project limits
  • Continue sign installation
  • General cleanup work throughout the project limits

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

VT Route 2A – Williston

Written by on September 26, 2019 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated daytime work schedule for the week beginning Monday, September 30, 2019.  

Monday through Friday – 7:00 a.m. to 5:30 p.m.:

  • Continue ditch and shoulder work
  • Potential signal work

Motorists should have minimal affect by this work.  Two-way traffic will be maintained.  Pedestrians will be detoured around the work area.

Monday through Friday – 7:00 p.m. to 6:00 a.m.:

  • Continue excavation for the widening of the east side of Route 2A.

Traffic control will be present allowing for one-lane of alternating traffic within the work area. Motorists should plan for delays.

   Please use caution while traveling thru the work zone.

The anticipated work schedule on VT 117 for the week beginning September 30, 2019

Written by on September 26, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

Monday thru Friday:

  • Weather permitting, continue paving abutting side roads and driveway tie-ins.
  • Continue shoulder work throughout the project limits
  • Weather permitting, pavement markings throughout the project limits
  • Continue sign installation
  • General cleanup work throughout the project limits

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

Rockingham Bridges I-91

Written by on September 26, 2019 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Saturday, September 28, 2019

Southbound I-91 bridge activities:

Saturday, Monday through Friday:

  • Continue work on Pier 2 for cap placement
  • Form work for placing shaft 1 at Pier 1
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Complete demolition of the old southbound Piers
  • Continue maintenance of traffic control devises.