The anticipated work schedule for the week beginning Saturday, September 7, 2019

Written by on September 6, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

Saturday, Monday through Friday:

  • Weather permitting, complete final paving on VT 117 to the VT Route 2 intersection in Richmond and begin paving abutting side road tie-ins.

Wednesday:

  • Installation of rumble strip 

Thursday & Friday:

  • Weather permitting, bridge joint work throughout the project.

EXPECT EXTENDED DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!



The anticipated work schedule on VT 117 for September 6, 2019

Written by on September 5, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • 7:00 a.m. Weather permitting, paving continues near the intersection of Skunk Hollow Road proceeding east. Motorists can expect a lane closure with 1-way alternating traffic.
  • Signal work at the intersection of VT-289.

EXPECT EXTENDED DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!

Rockingham Bridges I-91

Written by on September 5, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, September 09, 2019:

Southbound I-91 bridge activities:

Monday through Friday:

  • Continue Pier 3 cap work
  • Continue work on Pier 2
  • Grading at northbound abutment (#2) approach and begin form work
  • Work continues on the southbound abutment (#2) approach
  • Continue demolition of the existing southbound Pier 3 causing late work activities
  • Continue work at the new Pier 1 site
  • Continue maintenance of traffic control devises.

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!

VT Route 2A – Williston

Written by on September 5, 2019 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated daytime work schedule for the week beginning Sunday, September 8, 2019.  

Monday through Friday – 7:00 a.m. to 5:30 p.m.:

  • Continue work on the signal at the James Brown Drive intersection
  • Shaping & ditch cleanup after nighttime excavation work

Motorists should have minimal affect by this work.  Two-way traffic will be maintained.  Pedestrians will be detoured around the work area.

Sunday through Thursday – 7:00 p.m. to 6:00 a.m.:

  • Continue widening of the east side of Route 2A at the north end of the project working south.

Traffic control will be present allowing for one-lane of alternating traffic within the work area. Motorists should plan for delays.

   Please use caution while traveling thru the work zone.

The anticipated work schedule on VT 117 for September 5, 2019

Written by on September 4, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • 8:30 a.m. Weather permitting, expect a lane closure near the intersection of N. Williston Road proceeding east through the intersection of Skunk Hollow Road as paving continues.

MOTORISTS EXPECT EXTENDED DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!

The anticipated work schedule on VT 117 for September 4, 2019

Written by on September 3, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, paving continues eastbound from Skunk Hollow Road area.

MOTORISTS EXPECT EXTENDED DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!

The anticipated work schedule on VT 117 for the week beginning Tuesday, September 3, 2019

Written by on August 29, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

Tuesday through Saturday 7:00 a.m. to 6:00 p.m.

  • Weather permitting, continue final paving from Sand Hill Road, Jericho proceeding east to the VT Route 2 intersection in Richmond. 

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED WITHIN THE WORK ZONE!

VT Route 2A – Williston

Written by on August 29, 2019 in VT ROUTE 2A SAFETY IMPROVEMENTS
VT Route 2A – Williston

The following is the anticipated daytime work schedule for the week beginning Tuesday, September 3, 2019.  

Tuesday through Friday – 7:00 a.m. to 5:30 p.m.:

  • Continue work on the signal at the James Brown Drive intersection
  • Shaping & ditch cleanup after nighttime excavation work

Motorists should have minimal affect by this work.  Two-way traffic will be maintained.  Pedestrians will be detoured around the work area.

Tuesday through Friday – 7:00 p.m. to 6:00 a.m.:

  • Widening of the east side of Route 2A begins at the north end of the project

Traffic control will be present allowing for one-lane of alternating traffic within the work area. Motorists should plan for delays.

   Please use caution while traveling thru the work zone.

The work schedule on VT 117 for August 30, 2019 until noon

Written by on August 29, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Sample testing between Greenfield Road and N. Williston Road

MOTORISTS SHOULD EXPECT MINIMAL DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!

Rockingham Bridges I-91

Written by on August 29, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Tuesday, September 03, 2019:

Southbound I-91 bridge activities:

Tuesday through Friday:

  • Continue Pier 3 cap forms
  • Form and place Pier 2 section 4
  • Work continues on each abutment approaches
  • Demolition of the existing southbound Pier 3
  • Continue work at the new Pier 1
  • Continue maintenance of traffic control devises.

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!