Rockingham Bridges I-91

Written by on August 8, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, August 12, 2019:

Southbound I-91 bridge activities:

Monday through Friday:

  • Continue substructure removal
  • Continue Pier 3 shaft section 4
  • Continue Pier 2 shaft section 3
  • Work continues on each abutment approaches
  • Demolition of the existing southbound Pier 1
  • Continue maintenance of traffic control devises.

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!

The anticipated work on VT 117 for August 8, 2019

  • Ditch and shoulder clean up work throughout the project limits.
  • Milling side road approaches from the VT-289 intersection proceeding east.

Motorists can expect delays!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for August 7, 2019

  • Ditch and shoulder clean up work throughout the project limits.

Motorists can expect delays!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for August 6, 3019

  • Ditch and shoulder clean up work throughout the project limits.

Motorists can expect delays!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for the week beginning August 4, 2019

Monday through Friday:

  • Driveway paving preparation work
  • Shoulder clean up and ditch work

Wednesday and Thursday:

  • Milling the approaches on each end of the project along with all side road approaches

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

MOTORISTS, PLEASE SLOW DOWN!  SAFETY FIRST!

The anticipated work schedule on VT 117 for August 2, 2019

  • Begin milling driveway aprons approaches throughout the project limits
  • Ditch and shoulder clean up work throughout the project limits.
  • Signal work at the VT-289 intersection

Motorists can expect delays!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

Rockingham Bridges I-91

Written by on August 1, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, August 5, 2019:

Southbound I-91 bridge activities:

Monday through Friday:

  • Nighttime activity is done until further notice
  • Continue substructure removal
  • Continue placing Pier 3 shaft section 3
  • Continue Pier 2 shaft work
  • Grade work on the northbound abutment
  • Demolition of the southbound abutment
  • Continue maintenance of traffic control devises.

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!

Middlebury – Starksboro VT Route 116

Written by on August 1, 2019 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning August 05, 2019:

Monday thru Friday:

  • There is no work scheduled for this week.

The anticipated work schedule on VT 117 for August 1, 2019

  • Ditch and shoulder clean up work throughout the project limits.

Motorists can expect delays.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for July 31, 2019

  • Guardrail work continues between Skunk Hollow Road and Barber Farm Road.
  • Clean up work from the Essex/Jericho town line to Barber Farm Road

Motorists can expect delays.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!