The anticipated work schedule on VT 116

Written by on July 3, 2019 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning July 08, 2019:

Monday thru Friday:

  • There is no work scheduled for this week.

Rockingham Bridges I-91

Written by on July 3, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, July 08, 2019:

Monday through Friday (24-hour days) :

  • Continue removal of bridge deck

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!

The anticipated work schedule on VT 117 for the week beginning July 8, 2019

Monday & Tuesday

  • Weather permitting, continue paving from Barber Farm Road to the Essex/Jericho town line. MOTORISTS SHOULD EXPECT EXTENDED DELAYS!

Monday through Friday:

  • Guardrail replacement throughout the project limits

Traffic control will be present allowing for one lane of alternating traffic.

MOTORISTS SHOULD EXPECT DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for July 3, 2019

• Weather permitting, continue paving in the eastbound lane until approximately noon.

Motorists can expect long delays.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for July 2, 2019

• Weather permitting, continue paving from Rogers Lane proceeding west to Barber Farm Road in the eastbound lane.

Motorists can expect long delays.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule for the week beginning July 01, 2019

Monday through Wednesday @ noon:

  • Weather permitting, continue paving.

MOTORISTS SHOULD EXPECT DELAYS!

Traffic control will be present allowing for one lane of alternating traffic.

Work will resume on Monday, July 8, 2019 after the Independence Day holiday.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for June 28 & 29, 2019

Friday beginning mid-morning approx. 9:30 a.m. and Saturday beginning at approx. 7:00 a.m.:

• Weather permitting, continue paving from Rogers Lane to Bradley Bow Road.

Motorists can expect long delays.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

Rockingham Bridges I-91

Written by on June 27, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, July 01, 2019:

Monday 7 a.m. until Wednesday @ noon (24-hour days) :

  • Continue removal of bridge rail and curb

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!

The anticipated work schedule on VT 116

Written by on June 27, 2019 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning July 01, 2019:

Monday thru Friday:

  • There is no work scheduled for this week.

The anticipated work schedule on VT 117 for June 27, 2019

The anticipated work schedule on VT 117 for June 27, 2019

Beginning mid-morning approx. 9 am – 10 am start:

• Weather permitting, continue paving from the intersection of Route 2 in Richmond proceeding west.

Motorists can expect long delays.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

Top