The anticipated work schedule on VT 117 for the week beginning May 27, 2019

Monday:

  • No work due to the Memorial Day holiday

Tuesday thru Friday:

  • The second reclaiming process to begin to stabilize the roadway base between Skunk Hollow Road and the US Route 2/VT 117 intersection
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work schedule on VT 117 for May 23, 2019 until Noon only

  • Continue roadway excavation, shaping and drainage work between the Essex/Jericho town line and the intersection of US Route 2/VT 117
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.

The anticipated work schedule on VT 116

Written by on May 23, 2019 in Middlebury-Starksboro VT 116
The anticipated work schedule on VT 116

The following is an update to the work schedule for the week beginning May 27, 2019:

Monday:

  • No work due to the Memorial Day holiday.

Tuesday thru Friday:

  • General cleanup work throughout the project limits.

Motorists should expect minimal delays with traffic control present.

Rockingham Bridges I-91

Written by on May 23, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, May 27, 2019:

Monday:

No work due to the Memorial Day Holiday!

Tuesday thru Friday:

  • Work continues on the installation of the southbound crossover to include paving, shoulders & line striping.
  • Work continues on SB Piers #2 & #3.
  • Prep work on the existing southbound bridge for start of demolition
  • Installation of the southbound traffic control devises. 

REMINDERS:

  • JUNE 04, 2019 at 9:30am there will be a rolling roadblock for southbound motorists in preparation of opening the southbound crossover.  Motorists can anticipate approximately a 20-minute delay in their travels. If time does not allow for all work to be completed within the 20 minutes, there will be another rolling roadblock at 11:00am for approximately another 20-minute delay.
  • JUNE 4, 2019 THRU JUNE 6, 2019 the EXIT 6 SOUTHBOUND OFF-RAMP WILL BE CLOSED AT 9:30am June 4, 2019 until the end of the workday June 6, 2019.  Motorists will be detoured using Exit 7 Off-Ramp then follow the signed detour on Route 5 southbound.  All trucks over 14’ high will follow a signed detoured using Route 11.

KEEP YOUR HEADS UP AND YOUR CELL PHONE DOWN!

The anticipated work schedule on VT 117 for May 23, 2019

  • Continue roadway excavation, shaping and drainage work between the Essex/Jericho town line and the intersection of US Route 2/VT 117
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.

Rockingham I-91

Written by on May 22, 2019 in Rockingham Bridges-I91

*****  SOUTHBOUND CROSSOVER OPENING ****

TUESDAY, JUNE 04, 2019:

  • Beginning at 9:30am there will be a rolling roadblock for southbound motorists in preparation of opening the southbound crossover.  Motorists can anticipate approximately a 20-minute delay in their travels. If time does not allow for all work to be completed within the 20 minutes, there will be another rolling roadblock at 11:00am for approximately another 20-minute delay.

JUNE 4, 2019 THRU JUNE 6, 2019:

EXIT 6 SOUTHBOUND OFF-RAMP WILL BE CLOSED AT 9:30am June 4, 2019 until the end of the work day June 6, 2019.  Motorists will be detoured using Exit 7 Off-Ramp then follow the signed detour on Route 5 southbound.  All trucks over 14’ high will follow a signed detoured using Route 11.

NARROW LANES – USE CAUTION – REDUCE SPEED!

The anticipated work schedule on VT 117 for May 22, 2019

  • Continue roadway excavation, shaping and drainage work between the Essex/Jericho town line and the intersection of US Route 2/VT 117
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.

The anticipated work schedule on VT 117 for May 21, 2019

  • Continue roadway excavation, shaping and drainage work between Bradley Bow Road and Barber Farm Road
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work schedule for the week beginning May 20, 2019

Monday thru Friday @ noon:

  • Continue roadway shaping throughout the project limits
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work schedule on VT 117 for May 17, 2019

  • Continue roadway excavation, shaping and drainage work from Bradley Bow Road and Barber Farm Road
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

Top