The anticipated road work on VT 117 for May 08, 2019

  • Continued roadway excavation between the Essex/Jericho town line and Skunk Hollow
  • Continued roadway shaping between Rogers Lane and the US Route 2 & VT 117 intersection
  • 9am to 3pm VTrans will be working within the N. Williston Road intersection

Motorist should expect delays!
MOTORISTS PLEASE SLOW DOWN! SAFETY FIRST!



The anticipated work on VT 117 for May 07, 2019

• Continued roadway excavation between the Essex/Jericho town line and Skunk Hollow

• Continued roadway shaping between Rogers Lane and the US Route 2 & VT 117 intersection

• 9am to 3pm VTrans will be working within the N. Williston Road intersection

Motorist should expect delays!
MOTORISTS PLEASE SLOW DOWN! SAFETY FIRST!

The anticipated work schedule on VT 117 for the week beginning May 6, 2019

Monday thru Friday:

  • Continued roadway excavation and drainage improvements
  • Roadway shaping
  • Continued guardrail work

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work schedule on VT 116

Written by on May 2, 2019 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning May 06, 2019:

Monday thru Friday:

  • Weather permitting, side roads and driveway tie-ins throughout the project limits.
  • Pavement markings on abutting side roads throughout.
  • Bridge joint work throughout.
  • General cleanup work throughout.

Tuesday:

  • Installation of center line rumble strip throughout the project limits.

Motorists should expect delays with traffic control present allowing for 1-lane of alternating traffic within the construction zone.

The anticipated work on VT 117 for May 03, 2019

  • Fine grading/roadway shaping around the US Route 2/VT 117 intersection
  • Continued drainage improvements and guardrail work between the Essex/Jericho town line and Barber Farm Road.

Motorists should expect delays!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

Rockingham Bridges I-91

Written by on May 2, 2019 in Rockingham Bridges-I91

The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, May 06, 2019:

Monday thru Friday:

  • Work continues on the installation of the southbound crossover.
  • Work continues on SB Pier #3.
  • Continue work SB Pier #2 for placement of concrete footing and 1st shaft.
  • Continue maintenance on traffic control devises.

NARROW LANES – USE CAUTION!

The anticipated work schedule on VT 117 for May 02, 2019

  • 8:30am Reclaiming of the roadway surface continues in Richmond between the US Route 2/VT 117 intersection to Rogers Lane. Motorists can expect moderate to long delays.
  • 7:00am Continued drainage improvements and guardrail work between the Essex/Jericho town line and Barber Farm Road.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for May 01, 2019

  • Reclaiming of the roadway surface continues from north 
    of Bradley Bow Road, Jericho to Rogers Lane, 
    Richmond.
  • Continued drainage improvements from the
    Essex/Jericho town line to Skunk Hollow Road.
  • Continue guardrail work from the Essex/Jericho town line
    to Skunk Hollow Road.

USE CAUTION – DRIVE SLOW!

Rockingham Bridges I-91

Written by on April 29, 2019 in Rockingham Bridges-I91

The new northbound bridge is now open to one-lane of northbound traffic. The southbound bridge remains open to one-lane of southbound traffic until the new crossovers are built.

The Exit 6 On-Ramp is also reopened to traffic.

Use caution. Narrow Lanes.

The anticipated work schedule on VT 117 for April 30, 2019

  • Reclaiming of the roadway surface from Barber Farm Road to Rogers Lane. 
  • Continue guardrail work from Barber Farm Road to Skunk Hollow Road.
  • Continued drainage improvements from the Essex/Jericho town line to Skunk Hollow Road.

USE CAUTION – DRIVE SLOW!