Stephanie Barrett

Our specialty is in construction accounting, we contract with many businesses, offering a variety of accounting/payroll needs. In addition to accounting & bookkeeping services, we offer Public Relations work for job specific road/bridge construction and lease out fully operational office trailers.

VT 117 – November 27, 2018

Written by on November 26, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated weather dependent work schedule is as follows:

  • There is no work scheduled due to the weather forecast.
Motorists should expect minimal impact on traffic.
 
DRIVE SLOW – USE CAUTION!

Rockingham Bridges I-91

Written by on November 21, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, November 26, 2018:

********* IMPORTANT NOTIFICATION *********

Due to the unfortunate timing of winter rolling in, we will not be able to complete the driving surface of the northbound bridge this 2018 construction season, as anticipated.  The traffic pattern will remain as it has been during the construction of the northbound bridge until Spring 2019 when the temperatures allow for paving the new bridge deck and approaches. 

Construction activities will continue thru the winter and I will continue sending you notifications unless otherwise stated.

************************************************

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – 7:00am to 5:00pm:

  • Continue placement of the concrete barriers on the bridge.
  • Continue maintenance of traffic control devices, due to weather


I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!

The anticipated work on VT 116

Written by on November 21, 2018 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning Monday, November 26, 2018:

Monday thru Friday:

  • Weather permitting, continue driveway tie-ins throughout the project limits.
  • Weather permitting, continued painting pavement markings to include stop bars and crosswalks.
  • Placement of shoulder aggregate throughout the project limits.
  • General cleanup work throughout the project limits.

 

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

The anticipated work schedule on VT 117

Written by on November 21, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The following is an update to the work schedule for the week beginning Monday, November 26, 2018:

Monday:

  • Continued general clean-up work throughout the project limits.

Tuesday thru Friday:

  • Weather permitting, removal of the temporary lines between Tiffany Lane and the Essex/Jericho town line and repainting the lines at the correct locations along with other pavement markings.
  • Weather permitting, overlay of the line striping between the Essex/Jericho town line to the Route 2/VT 117 intersection.
  • Guardrail work between Tiffany Lane and the Essex/Jericho town line.
  • Signal work at the VT 289 off ramp.


Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

VT 117 – November 21, 20018

Written by on November 20, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated weather dependent work schedule is as follows:

  • General clean-up work throughout the project limits.
Motorists should expect minimal impact on traffic.
 
DRIVE SLOW – USE CAUTION!

VT 117 – NOVEMBER 20, 2018

Written by on November 19, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated weather dependent work schedule is as follows:

  • Shoulder work between Sand Hill Road and the Essex/Jericho town line.
  • Begin removal of portable message boards on project.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

Rockingham Bridges I-91

Written by on November 15, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Sunday, November 18, 2018:

I-91 northbound bridge activities:

Sunday thru Tuesday – 5:00pm to 5:00am
Monday thru Wednesday – 7:00am to 5:00pm:

  • Continue work on both bridge approaches.
  • Continue placement of the concrete barriers on the bridge.

Thursday & Friday:

  • No work due to the Thanksgiving Day holiday.


I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!

The anticipated work schedule on VT 117

Written by on November 15, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The following is the anticipated work schedule for the week beginning Monday, November 19, 2018 – Please note at this time of the year work can be weather dependent.

Monday thru Wednesday @ noon:

  • Weather permitting, temporary pavement markings throughout the project limits.
  • Weather permitting, continued paving driveway tie-ins between Sand Hill Road and Tiffany Lane.
  • Signal work at the VT 289 off ramp.

 Wednesday @ noon thru Friday:

  • No work due to the Thanksgiving Day holiday.

COMMUTING MOTORISTS SHOULD SEEK ALTERNATE ROUTES.  EXPECT DELAYS DURING PEAK HOURS!

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!

The anticipated work schedule on VT 116

Written by on November 15, 2018 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning Monday, November 19, 2018:

Monday thru Friday:

  • Weather permitting, continue driveway tie-ins between Bristol Notch Road and RT17/116 intersection.
  • Weather permitting, pavement markings to include side road and crosswalks.
  • Placement of shoulder aggregate throughout the project limits.
  • General cleanup work throughout the project limits.

Thursday & Friday:

  • No work due to the Thanksgiving Day holiday


Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

VT 117 – November 16, 2018

Written by on November 15, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

Due to the weather forecast, there is no work scheduled for the day.

Top