Rockingham Bridges I-91

Written by on October 4, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, October 08, 2018.

 I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:

  • Begin construction on the northbound abutment approach.
  • Begin placing concrete deck segments.
  • Continue installation deck reinforcing.
  • Complete forming back wall at the southern abutment.

Please drive slow and use caution while traveling thru the construction zone.

VT Route 2A, Williston

Written by on October 4, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated work schedule for the week beginning Monday, October 08, 2018:

Monday:

  • No work due to the Columbus Day holiday.

Tuesday thru Thursday:

  • Complete the installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic on Eastview during this work.

Tuesday thru Friday:

  • Installation of the flashing beacons for/at the Bittersweet crosswalk.
  • Clean up work within the Morgan Parkway area from the tree cutting.

Motorists should expect minimal delays and use caution while traveling thru the work zone.

Anticipated schedule on VT 117

Written by on October 4, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The following is the anticipated work schedule for the week beginning Monday, October 8, 2018:

 Monday:

  • No work due to the Columbus Day holiday.

 Tuesday thru Friday:

  • Culvert work continues between Barber Farm Road and the Jericho/Richmond town line.
  • Structure rehabilitation work continues between the VT-289 intersection to Tiffany Lane.
  • Shoulder/ditch work continues from Greenfield Road to Tiffany Lane.
  • Continued guardrail work between N. Williston Road and Tiffany Lane.

 Wednesday thru Friday:

  • Weather permitting, paving resumes from VT-289 to Tiffany Lane.

COMMUTING MOTORISTS SHOULD SEEK ALTERNATE ROUTES.  EXPECT DELAYS DURING PEAK HOURS!

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!

The anticipated work schedule for VT Route 116

Written by on October 4, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, October 08, 2018:

Monday:

  • No work due to the Columbus Day holiday.

Tuesday thru Saturday:

  • Weather permitting, final paving to begin south of Bristol Village to East Middlebury.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

VT 117 – October 08, 2018

Written by on October 4, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
7:00am until Noon due to the holiday weekend:
  • Shoulder / ditch work will continue between Sand Hill Road and Greenfield Road.
  • Continued culvert work Barber Farm Road and Bradley Bow Road.
  • Brush clearing around Skunk Hollow Road.
  • Guardrail work will continue between N. Williston Road and Sand Hill Road.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

VT 117 – October 04, 2018

Written by on October 3, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Shoulder / ditch work will resume between N. Williston Road and Greenfield Drive
  • Continued culvert work Barber Farm Road and Bradley Bow Road.
  • Guardrail work will continue between N. Williston Road and Sand Hill Road.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

VT 117 – October 03, 2018

Written by on October 2, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Shoulder / ditch work will resume between Sand Hill Road and Greenfield Drive
  • Continued culvert work around the Jericho/Richmond town line.
  • Guardrail work will continue between N. Williston Road and the Essex/Jericho town line.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

VT 117 – October 02, 2018

Written by on October 1, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Weather permitting, paving the entrance apron on Mall Drive.
  • Continued structure rehab work between VT-289 and Tiffany Lane.
  • Continued culvert work around the Jericho/Richmond town line.
  • Guardrail work will continue between N. Williston Road and the Essex/Jericho town line.
  • Placement of gravel to abutting driveway aprons to ease the transition onto VT 117 until the aprons get paved.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

Anticipated work schedule on VT 117

Written by on September 27, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The following is the anticipated work schedule for the week beginning Saturday, September 29, 2018:

Saturday, Monday & Tuesday:

  • Weather permitting, completion of base course paving from Sand Hill Road to Tiffany Lane.

 Monday thru Friday:

  • Culvert work continues from the Essex/Jericho town line to the US Route 2 intersection.
  • Structure rehabilitation work continues within the VT-289 intersection to Tiffany Lane.
  • Shoulder work from Tiffany Lane to the Essex/Jericho town line.
  • Continued guardrail work between the Essex/Jericho town line and Tiffany Lane.
  • Weather permitting, paving within the VT-289 intersection.

 

COMMUTING MOTORISTS SHOULD SEEK ALTERNATE ROUTES.  EXPECT DELAYS DURING PEAK HOURS!

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!

VT Route 2A

Written by on September 27, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated work schedule for the week beginning Monday, October 01, 2018:

 Monday thru Friday:

  • Final work on the installation of the pedestrian crosswalk at Bittersweet Circle to include pavement markings.

 Monday thru Wednesday:

  • Installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic on Eastview during this work.

 Motorists should expect minimal delays and use caution while traveling thru the work zone.