Stephanie Barrett
Our specialty is in construction accounting, we contract with many businesses, offering a variety of accounting/payroll needs. In addition to accounting & bookkeeping services, we offer Public Relations work for job specific road/bridge construction and lease out fully operational office trailers.
The following is an update of the construction to take place for the week beginning Monday, September 21, 2020.
Monday through Friday: 6:00 a.m. to 5:00 p.m.:
- Bridge deck work continues to include tying in deck steel
- Continue work on the approach slab at the northbound abutment
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, September 14, 2020.
Monday through Friday: 6:00 a.m. to 5:00 p.m.:
- Bridge deck work continues to include tying in deck steel
- Continue backfilling and forming southbound abutment
- Placement of concrete in the approach slab at the northbound abutment
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, September 7, 2020.
Monday: No work due to the Labor Day holiday
Tuesday through Friday: 6:00 a.m. to 5:00 p.m.:
- Bridge deck work continues including pouring of the first concrete section
- Backfilling at the southbound abutment
- Forming the approach at the northbound abutment
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, August 31, 2020.
Monday through Friday- 6:00 a.m. to 5:00 p.m.:
- Bridge deck work to continue
- Continue work on the abutments
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, August 24, 2020.
Monday through Friday- 6:00 a.m. to 5:00 p.m.:
- Bridge deck work to continue
- Continue work on the abutments to include backfilling at the northbound abutment approach
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, August 17, 2020.
Monday through Friday- 6:00 a.m. to 5:00 p.m.:
- Bridge deck work to continue including installing rebar
- Continue work on the abutments to include concrete placement on the southbound end
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, August 10, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Monday through Friday- 6:00 a.m. to 5:00 p.m.:
- Bridge deck work to continue including installing rebar
- Continue work on the abutments to include concrete placement on the southbound end
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, August 03, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Monday through Friday- 6:00 a.m. to 5:00 p.m.:
- Bridge deck work to continue including installing rebar
- Continue work on the abutments to include southbound concrete placement
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
Please note the Vermont State Police will be setting up radar within the construction zone. Follow the posted speed limit.
The following is an update of the construction to take place for the week beginning Monday, July 27, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Monday through Friday- 6:00 a.m. to 5:00 p.m.:
- Bridge deck work to continue
- Placement of concrete and other work at the northbound abutment
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, July 20, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Monday through Friday- 6:00 a.m. to 5:00 p.m.:
- Bridge deck work to continue
- Placement of concrete and other work at the northbound abutment
- Relocation of various cranes between I-91 decking and the construction yard on Golden Hill Road
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
Connect