The anticipated schedule for VT Route 116

Written by on September 13, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, September 17, 2018:

Monday:  No work scheduled

Tuesday thru Friday:

  • Prepping side roads and driveway tie-ins in preparation of final paving from Bristol proceeding south to the end of the project limits in Middlebury.

Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

VT 117 – September 13, 2018

Written by on September 12, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule is as follows:

Motorists should expect long delays between 2pm & 7pm between N. Williston Road and Sand Hill Road

  • Weather permitting, continued installation of cold mix between the Essex/Jericho town line and Sand Hill Road.
  • Shoulder clean up and ditch work continues between Valley View Drive and Tiffany Lane.

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!

Commuting motorists should seek alternate routes.  Expect delays during peak hours!

VT 117 – September 12, 2018

Written by on September 11, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule is as follows:

Motorists should expect long delays between 2pm & 7pm between N. Williston Road and Sand Hill Road

  • Weather permitting, continued installation of cold mix between the Essex/Jericho town line and Sand Hill Road.
  • Underdrain work continues between Barber Farm Road and the Jericho/Richmond town line.
  • Shoulder clean up and ditch work continues between Valley View Drive and Tiffany Lane.

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!

Commuting motorists should seek alternate routes.  Expect delays during peak hours!

VT 117 – September 11, 2018

Written by on September 10, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule is as follows:

  • Underdrain work continues between Barber Farm Road and the Jericho/Richmond town line.
  • Slope stabilization work continues near the VT-117 & US Route 2 intersection.

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!

Commuting motorists should seek alternate routes.  Expect delays! 

VT 117 – September 08, 2018

Written by on September 7, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

There will not be any work as originally anticipated.

Use caution while traveling thru the construction zone! 

PLEASE DRIVE SLOW!

 

The following is the weekly work schedule on VT 117

Written by on September 6, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

For the week beginning Saturday, September 08, 2018:

 Saturday:

  • Weather permitting & tentatively, continued installation of cold mix from the Essex/Jericho town line proceeding west to Tiffany Lane.

 Monday thru Friday:

  • Weather permitting, continued installation of cold mix from the Essex/Jericho town line proceeding west to Tiffany Lane.
  • Underdrain and slope stabilization work continues between Barber Farm Road and the US Route 2 intersection.

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!

Commuting motorists should seek alternate routes.  Expect delays during peak hours!

VT 117 – September 07, 2018

Written by on September 6, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The work schedule for Friday, September 07, 2018 is as follows:

  • Continued underdrain and slope stabilization work between Barber Farm Road and the Jericho/Richmond town line.
  • Shoulder cleanup between VT-289 and Tiffany Lane.

Traffic control is present allowing for one lane of alternating travel.

USE CAUTION – DRIVE SLOW!

The following is the anticipated schedule for Bridge #8:

Written by on September 6, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, September 10, 2018:

  • There will be no work scheduled on this project until further notice.

 

VT Route 2A:

Written by on September 6, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated work schedule for the week beginning Monday, September 10, 2018:

 Monday and Tuesday:

  • Complete installation of construction signage.

Wednesday:

  • Tree removal on the east side of Route 2A between Morgan Parkway and Eastview Circle.

Thursday & Friday:

  • Excavation for the removal of the tree trunks left on Wednesday in anticipation of tree planting the following week.

 

Motorists should expect minimal delays and use caution while traveling thru the work zone.

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on September 6, 2018 in Rockingham Bridges-I91

For the week beginning Monday, September 10 , 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am:
Monday thru Friday – Daytime:

  • Continue installation of bridge deck form work and overhang.
  • Continue removal of temporary supports that held the beams and forms.
  • Begin forming back wall at the northern abutment.

REED & REED WILL CONTINUE WORKING A NIGHT SHIFT.