Next week’s anticipated schedule on VT 117:

Written by on August 10, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

For the week beginning Saturday, August 11, 2018:

 Saturday:

  • Grading the roadway between VT-289 and Tiffany Lane.

 Monday & Tuesday:

  • Grading continues between Sand Hill Road and the Essex/Jericho Town line.
  • Culvert replacement work continues near N. Williston Road.

Wednesday thru Friday:

  • 2nd reclaiming phase to begin which includes adding a stabilize agent to the subbase. This agent takes time to cure causing a maximum of 2 hour lane restriction after installation is completed.

 

Motorists please be aware:

  • There will not be a center line from the Essex/Jericho Town line to Tiffany Lane
  • Rough roadway surface
  • Please drive slowly & use caution!

 

Commuting motorists should seek alternate routes.  Expect delays during peak hours!

VT 117 – August 10, 2018

The anticipated work activities are as follows:

  • Continued removal of unsuitable material and backfilling with new material to proper grade from the Essex/Jericho town line to Sand HIll Road.
  • Continued culvert work approximately 500′ from Tiffany Lane.
  • Slope stabilization work continues within the Skunk Hollow Road area.

Continued road maintenance as needed.

The following is the anticipated schedule for Bridge #8:

Written by on August 9, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, August 13, 2018:

 Monday thru Friday:

  • Continued removal of old concrete piers
  • Installation of bridge plug joints on both ends of the bridge
  • General cleanup work throughout

 

Motorists should be aware of traffic control allowing for one lane of alternating traffic.

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on August 9, 2018 in Rockingham Bridges-I91

For the week beginning Monday, August 13, 2018:

I-91 northbound bridge activities:

 Monday thru Friday:

  •  Continued preparation work on the set girders to include concrete pours in anticipation of pouring the new bridge decking.

The following work schedule on VT 116

Written by on August 9, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, August 13, 2018:

 Monday thru Wednesday:

  •  Completion of culvert crossing between Airport Road & VT Route 125 in E. Middlebury – Traffic will be 1 lane thru this area controlled by a traffic signal.

Wednesday thru Friday:

  • Weather permitting, final paving to begin at Meehan Road, Bristol proceeding north to the end of the project limits in Starksboro.

VT 117 – August 09, 2018

The anticipated work activities are as follows:

  • Continued removal of unsuitable material and backfilling with new material to proper grade from VT-289 off ramp to Tiffany Lane.
  • Continued culvert work near the Essex/Jericho town line.
  • Slope stabilization work continues within the Skunk Hollow Road area.

Continued road maintenance as needed.

VT 117 – August 08, 2018

The anticipated work activities are as follows:

  • Continued removal of unsuitable material and backfilling with new material to proper grade between Greenfield and No. Williston Roads.
  • Continued culvert work near the Essex/Jericho town line.
  • Excavation work continues from VT-289 off ramp to Tiffany Lane.

Continued road maintenance as needed.

VT 117 – August 07, 2018

The anticipated work activities are as follows:

  • Continued removal of unsuitable material and backfilling with new material to proper grade between VT-289 and Sand Hill Road.
  • Continued slope stabilization work between Skunk Hollow & Barber Farm Roads.
  • Excavation work continues from VT-289 off ramp to Tiffany Lane.

Continued road maintenance as needed.

Next week’s anticipated schedule on VT 117:

Next week’s anticipated schedule on VT 117:

Slope Stabilization

For the work schedule for the week beginning Saturday, August 4, 2018:

Saturday, Monday thru Friday:
• Continued removal of unsuitable material and backfilling with new material to proper grade from N. Williston Road proceeding westbound to Tiffany Lane.
• Continued slope stabilization work between Skunk Hollow & Barber Farm Roads.

Monday thru Wednesday:
• Excavation work continues from VT-289 off ramp to Tiffany Lane.

Thursday & Friday:
• Culvert replacement continues between N. Williston Road and the Essex/Jericho Town line.

ROADWAY MAINTENANCE THROUGHOUT THE PROJECT!

MOTORISTS PLEASE BE AWARE:
 There will not be a center line from the Essex/Jericho Town line to Tiffany Lane
 Rough roadway surface
 Please drive slowly & use caution!

Commuting motorists should seek alternate routes. Expect delays during peak hours!

The following is the anticipated schedule for Bridge #8:

Written by on August 2, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, August 06, 2018:

 Monday thru Friday:

  • Removal of old concrete piers
  • Installation of bridge plug joints
  • General cleanup work throughout

Motorists should be aware on Monday there will be traffic control allowing for one lane of alternating traffic.

There will be 2 lanes of traffic open during Addison County Field Days.