VT 117 – August 3, 2018

The anticipated work schedule is as follows:

  • Excavating sections of the roadway from the Essex /Jericho Town line working westbound to Tiffany Lane.
  • Begin removing unsuitable material and backfilling with new material to proper grade between VT 289 and Tiffany Lane.

ROADWAY MAINTENANCE AS NEEDED!    SLOW DOWN FOR ROUGH ROAD CONDITIONS!

EXPECT DELAYS DURING PEAK HOURS WITH ONE-LANE OF ALTERNATING TRAFFIC.

Motorists please be aware:
 There will not be a center line from the Essex/Jericho Town line to Tiffany Lane.
 Rough roadway surface.

Commuting motorists should seek alternate routes. 

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on August 2, 2018 in Rockingham Bridges-I91

For the week beginning Monday, August 06, 2018:

I-91 northbound bridge activities:

 Monday thru Friday:

  •  Continued preparation work on the set girders to include concrete pours in anticipation of pouring the new bridge decking.

 

The following work schedule on VT 116

Written by on August 2, 2018 in Middlebury-Starksboro VT 116
The following work schedule on VT 116

The following is an update to the work schedule for the week beginning Monday, August 06, 2018:

Monday thru Friday:

  • Continued culvert work between Airport Road & VT Route 125 in E. Middlebury – Traffic will be 1 lane thru this area controlled by a traffic signal.
  • Relocation and/or replacement of various mailboxes throughout the project due to the widening of the roadway – homeowners have been directly notified of this work

Wednesday:

  • Asphalt curb installation on “Stoney Hill” between So. Airport Road & Lovers Lane.

Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

Culvert Work 7/31/18

VT 117 – August 2, 2018

The anticipated work schedule is as follows:

  • Reclaiming continues between VT 289 and Tiffany Lane in the westbound lane.
  • Slope stabilization work between Skunk Hollow Road and Barber Farm Road in Jericho.
  • Drainage enhancement work continues from No. Williston Road to Essex/Jericho Town line.

ROADWAY MAINTENANCE AS NEEDED!

SLOW DOWN FOR ROUGH ROAD CONDITIONS!

EXPECT DELAYS DURING PEAK HOURS WITH ONE-LANE OF ALTERNATING TRAFFIC.

Motorists please be aware:
 There will not be a center line from the Essex/Jericho Town line to Tiffany Lane.
 Rough roadway surface.

Commuting motorists should seek alternate routes. 

VT 117 – August 01, 2018

The anticipated work schedule is as follows:

  • Reclaiming continues between VT 289 and Tiffany Lane.
  • Slope stabilization work between Skunk Hollow Road and Barber Farm Road in Jericho.
  • Culvert replacement approximately 1000′ east of No. Williston Road continues

ROADWAY MAINTENANCE AS NEEDED!

SLOW DOWN FOR ROUGH ROAD CONDITIONS!

EXPECT DELAYS DURING PEAK HOURS WITH ONE-LANE OF ALTERNATING TRAFFIC.

Motorists please be aware:
 There will not be a center line from the Essex/Jericho Town line to Tiffany Lane.
 Rough roadway surface.

Commuting motorists should seek alternate routes. 

 

VT 117 – July 31, 2018

The anticipated work schedule is as follows:

  • Reclaiming continues between Sand Hill Road and VT 289.
  • Slope stabilization work between Skunk Hollow Road and Barber Farm Road in Jericho.
  • Begin culvert replacement approximately 1000′ east of No. Williston Road

ROADWAY MAINTENANCE AS NEEDED!

Motorists should expect delays with traffic control present allowing for one-lane of alternating traffic.

SLOW DOWN FOR ROUGH ROAD CONDITIONS!
EXPECT DELAYS DURING PEAK HOURS!

Bridge #8 – VT 117

Written by on July 28, 2018 in BRIDGE 8 VT ROUTE 17
Bridge #8 – VT 117

THE BRIDGE IS NOW OPEN TO THRU TRAFFIC.

Motorists should be aware of traffic control during the work week allowing for one-lane of alternating travel thru the construction area.

The following is the anticipated schedule for Bridge #8:

Written by on July 26, 2018 in BRIDGE 8 VT ROUTE 17
The following is the anticipated schedule for Bridge #8:

Paved Bridge#8 Deck

Weather permitting, Bridge #8 will be opened to thru traffic tomorrow, July 27, 2018.

 

The following is the anticipated work schedule for the week beginning Monday, July 30, 2018.

 Monday thru Sunday:

  •  Miscellaneous clean-up work.

 

Traffic control will be present during the daytime hours allowing for one-lane of alternating traffic over the bridge site.

The bridge was opened to traffic on/before the anticipated schedule!

The anticipated work schedule on VT 117:

For the week beginning Monday, July 30, 2018:

Monday thru Friday:
• Continue reclaiming the roadway from Sand Hill Road proceeding west to Tiffany Lane.
• Continue underdrain work from the Essex/Jericho Town line proceeding east.
• Shoulder/slope stabilization from the Essex/Jericho Town line proceeding east.
• Culvert replacement between N. Williston Road and the Essex/Jericho Town line.
• ROADWAY MAINTENANCE THROUGHOUT THE PROJECT!

Motorists please be aware:
 There will not be a center line from the Essex/Jericho Town line to Tiffany Lane.
 Rough roadway surface.
 Please drive slowly & use caution!

Commuting motorists should seek alternate routes. Expect delays during peak hours!

 

 

VT 117 – July 26, 2018

The anticipated work schedule is as follows:

  • Reclaiming continues in the east bound lane from the Essex/Jericho Town Line proceeding to Sand Hill Road.
  • Continue shoulder work around the VT 289 interchange
  • Continued underdrain work within the Barber Farm Road area

ROADWAY MAINTENANCE AS NEEDED!

Motorists should expect delays with traffic control present allowing for one-lane of alternating traffic.

SLOW DOWN FOR ROUGH ROAD CONDITIONS!
EXPECT DELAYS DURING PEAK HOURS!